Fairchild House, Southampton

Date

July 2019

Remedials

All Corridors/Risers

Client

PPNL

A 45 Bed Student Accommodation in the heart of Southampton. After a fire compartment survey conducted by others Evolutions Fire were able to completely overhaul the property and rectify all of the compartmentation defects.

The findings from our report revealed a significant number of defects throughout the five blocks present onsite. Thankfully the client were quick to action the remedials from the findings of the report to protect the lives of those who reside within in the unfortunate event of a fire. Every Fire Wall & Ceiling throughout the entire project was inspected, rectified and restored to a fire resisting standard proven by tested and traceable materials.

Some of the significant defects were the following;

  • Missing Closer devices to all Plastic Pipes
  • Inadequate Fire Stopping to Communal Corridors, Toilet Risers, Electrical Intakes, Student Rooms
  • Incomplete Corridor Partitions

How we Completed

Working closely with the managing body CRM Students Evolutions devised a phased, floor by floor approach to each block. Ensuring all risers where completed before moving onto the next floor. By doing it in this method Evolutions removed wasted trips and consolidated noise and disturbance to a select time window.

The Goal

To rectify all corridors, risers with defective compartmentation. In doing so would allow the building to operate as per its fire strategy and provide the nessecary time to escape & for fire services to operate.

Final Results

The entire site was completed in a period of 6 weeks, the works commenced at the start of the 6 week school holiday. Thus allowing minimal disruption to the university students who remained and not impacting on the buildings operation.